An early estimate is not wrong because it is uncertain. It is wrong if it claims more accuracy than the definition behind it supports.
The situation
Cost estimates mature with project definition. AACE classifies estimates from Class 5 (concept screening) to Class 1 (check estimate), each with an expected accuracy range. Contingency should come from risk analysis, not a flat percentage.
Industry practice groups estimates into classes by the level of project definition. Early estimates rely on capacity factors and analogues and carry wide ranges. Later estimates use quantities and quotes and carry narrower ranges.
Contingency covers uncertainty within the defined scope. It is not a fund for scope changes. It should be set from a risk analysis rather than a flat percentage, and released as risks retire.
Keep escalation, currency effects and known allowances separate from contingency so each can be managed.
Always present the estimate class, the accuracy range and the main assumptions. A single number without these invites misunderstanding.
Compare estimates with similar completed projects. Large differences either reveal scope gaps or genuine advantages that need explaining.
We prepare and review cost estimates at each stage, set contingency from risk analysis and benchmark against comparable projects.
Berlin Brandenburg Airport's final cost was several times early budgets. This is a public example of what happens when early estimates are treated as firm before definition is mature.
Read the investigation / sourceA board approved a project on a concept-stage estimate with a 10% contingency. Once the design matured, the cost rose by more than half and the project had to be re-sanctioned.
Links go to the publisher's official page (ISO, IEC, BSI, API, NFPA, HSE and others). Most standards must be bought from the publisher.
Take this briefing with you
A one-to-two page PDF summary: situation, diagram, key takeaways, consequences, examples and standards.