A field development plan joins subsurface, wells, facilities, operations and economics into one story. Regulators, partners and lenders all read it for different reasons.
The situation
A field development plan (FDP) sets out how a resource will be developed: subsurface description, well plan, facilities concept, export, costs, schedule, HSE, decommissioning and economics. It is often the key regulatory and investment document.
A field development plan (FDP) sets out how a resource will be developed and produced. It underpins regulatory approval, partner commitment and financing.
The most common weakness is sections written in isolation. Profiles should match facility capacity, schedules should match drilling plans, and costs should match the scope.
Show how the plan can adapt to upside or downside cases, for example space for extra wells or phased facility expansion.
We prepare and review field development plans and concept selection reports, with a focus on facilities and integration.
An FDP sized the facilities on optimistic reserves. Production plateaued well below capacity, leaving costly unused equipment and higher unit costs.
An FDP left decommissioning costs out of its economics. When the regulator required financial security later, project value fell sharply.
Links go to the publisher's official page (ISO, IEC, BSI, API, NFPA, HSE and others). Most standards must be bought from the publisher.
Take this briefing with you
A one-to-two page PDF summary: situation, diagram, key takeaways, consequences, examples and standards.