Start-up is the highest-risk period in a plant's life. A staged sequence, from utilities to export, with clear hold points, keeps it controlled.
The situation
Gas plant start-up follows a defined sequence: utilities, purging and inerting, leak testing, pressurisation, cooling of cold sections, then controlled introduction of feed and ramp-up. Start-ups are one of the highest-risk operating modes.
Bringing every system online at once makes problems hard to diagnose and risks upsets cascading through the plant. A staged sequence brings each system up, stabilises it and confirms it before the next.
Each stage ends with checks: stable operation, alarms clear, specifications met. Do not move on to the next stage with known problems.
Clear roles, a start-up leader, and regular briefings between control room and field teams. Plan shift handovers around critical steps.
Restarts after shutdowns follow the same logic but often feel routine. That is when steps get skipped.
We prepare start-up and commissioning procedures and support operations teams through first start-up and major restarts.
The Texas City explosion occurred during unit start-up, when a tower was overfilled while instruments were not working correctly and procedures were not followed. The CSB noted that start-up and shutdown are periods of elevated risk.
Read the investigation / sourceAt Longford, attempts to restart flow into an exchanger that had become extremely cold led to brittle fracture. Restart procedures for cold equipment are critical.
Read the investigation / sourceLinks go to the publisher's official page (ISO, IEC, BSI, API, NFPA, HSE and others). Most standards must be bought from the publisher.
Take this briefing with you
A one-to-two page PDF summary: situation, diagram, key takeaways, consequences, examples and standards.