Drilling, maintenance, projects, inspections and shutdowns all compete for the same people, beds, cranes and process conditions. One integrated plan exposes the clashes before they happen.
The situation
Integrated activity planning (IAP) brings maintenance, projects, inspection, wells and operations activities into one plan across time horizons, resolving conflicts in resources, beds, permits and SIMOPS before they reach the field.
Each department plans its own work. When the plans meet on site, they clash: two crews need the same crane, a shutdown overlaps a drilling campaign, or bed space runs out.
One plan that holds all significant activities, with shared resources and constraints visible to everyone. It is reviewed regularly by the people who own each activity.
Fewer clashes, better use of shutdown windows, and less unplanned deferment from work that conflicts with production.
We help assets set up integrated activity planning, define planning horizons and run the review cycle.
On Piper Alpha, maintenance and production activities were not effectively coordinated across shifts and work groups. Integrated planning and SIMOPS control address exactly this risk.
Read the investigation / sourceA pipeline pigging campaign and a compressor overhaul were planned separately in the same week. The clash forced one to be cancelled at short notice, wasting mobilised resources and extending deferment.
Links go to the publisher's official page (ISO, IEC, BSI, API, NFPA, HSE and others). Most standards must be bought from the publisher.
Take this briefing with you
A one-to-two page PDF summary: situation, diagram, key takeaways, consequences, examples and standards.