Velocity and pressure-drop limits get a design close quickly. Two-phase flow, erosion, noise and relief lines are where hand rules run out and proper calculation takes over.
The situation
Line sizing balances pressure drop, velocity, erosion, noise, vibration and cost. Rules of thumb (velocity limits, ΔP per 100 m, API RP 14E erosional velocity) are useful for screening. Final sizes should be confirmed by hydraulic calculation.
Early in design, quick sizing by velocity and pressure-drop limits gives line sizes good enough for layout, cost estimates and hydraulic checks. Experienced engineers carry a set of these numbers for each service.
Record the basis for each line size in a line list. When flow rates change during design or operation, the basis shows quickly which lines need rechecking.
We prepare hydraulic calculations, line lists and debottlenecking checks, and we build lightweight calculation tools for rapid screening.
A choke-downstream line was sized on pressure drop alone. Sand at high velocity eroded a bend within months, which was found by chance during an inspection. Sizing for erosional velocity, or adding sand monitoring, would have prevented it.
Undersized small-bore connections on a high-velocity gas line suffered fatigue cracking from vibration. Industry guidance recommends screening for flow-induced vibration and acoustic fatigue at design stage.
Links go to the publisher's official page (ISO, IEC, BSI, API, NFPA, HSE and others). Most standards must be bought from the publisher.
Take this briefing with you
A one-to-two page PDF summary: situation, diagram, key takeaways, consequences, examples and standards.