Management of change: fast for small changes, rigorous for big ones
Back to Knowledge Base
Process Safety 6 minKnowledge Base

Management of change: fast for small changes, rigorous for big ones

2026-11-15

Many major incidents trace back to a change that was not properly assessed. A good MOC process is proportionate, clear about who decides, and finishes the paperwork after the change.

The situation

Management of change (MOC) ensures that changes to plant, process, procedures, organisation or software are reviewed for hazards and approved before they are made. Temporary changes and 'like-for-like' replacements are frequent weak spots.

What counts as a change

Any change to equipment, chemicals, operating limits, procedures, software, organisation or staffing that could affect safety or integrity. Like-for-like replacements are usually excluded, but the definition must be clear.

Diagram: Management of change
Figure: Atticus Energy, generic illustration.

Keys to a good process

  • Proportionate. Small, low-risk changes move quickly; large ones get full review.
  • Clear authority. Approvers are matched to the level of risk.
  • Multi-disciplinary review. Process, mechanical, instrumentation, electrical, operations and HSE as needed.
  • Pre-start-up check. Confirm the change was built as approved before it goes live.
  • Close-out. Drawings, procedures, training and relief registers updated.

Temporary changes

Temporary repairs and bypasses need an expiry date and tracking. Many "temporary" changes outlive their review.

Organisational change

Changes to staffing, roles and contractors can weaken barriers just as much as physical changes, and should go through a similar assessment.

Measuring health

Track open MOCs, overdue temporary changes and outstanding documentation updates. A growing backlog is an early warning.

Key Takeaways

  • Define clearly what counts as a change.
  • Scale review and approval to the risk.
  • Track temporary changes to expiry.
  • Close out documentation, not just the physical work.

How Atticus helps

We review MOC procedures and backlogs, support technical assessments of changes and help sites set up proportionate screening.

Real-world examples

Documented incident

Flixborough — HSE case study (1974)

The Flixborough bypass pipe was a temporary modification made without engineering design or hazard review. It failed catastrophically. This is the classic case that made MOC a standard element of process safety management.

Read the investigation / source
Documented incident

BP Amoco thermal decomposition incident — CSB (2001)

At a polymer plant, workers died when a vessel was opened during a start-up problem. The CSB identified design and management-of-change weaknesses in how a new process had been introduced.

Read the investigation / source

If you get it wrong

  • Hazards introduced without review.
  • Drawings, procedures and training out of date.
  • Temporary changes that quietly become permanent.
  • Major accidents traced back to small, unreviewed changes.

Relevant standards

Links go to the publisher's official page (ISO, IEC, BSI, API, NFPA, HSE and others). Most standards must be bought from the publisher.

Further reading

Take this briefing with you

A one-to-two page PDF summary: situation, diagram, key takeaways, consequences, examples and standards.