A project is not finished when construction is complete. It is finished when trained people, procedures, spares and systems are ready to operate the facility safely and reliably.
The situation
Operational readiness (OR) prepares people, processes, systems and spares so that a new or modified facility can be started and operated safely and reliably from day one. OR activities should begin at Select stage, not just before handover.
Common start-up problems are untrained staff, missing procedures, spares not delivered, maintenance systems not loaded and documentation that does not match the plant. These are not construction problems; they are readiness problems.
Readiness work should start in design. Operators who review designs catch maintainability and operability issues while they are cheap to fix.
Readiness reviews before start-up confirm that each workstream is complete. Use a clear checklist, but test it in the field.
We plan and run operational readiness programmes, write procedures and support readiness reviews before start-up.
The Kleen Energy explosion happened during commissioning activities at a new power plant. The CSB found that hazardous commissioning practices were used without adequate hazard analysis, which is a readiness and assurance gap.
Read the investigation / sourceCritical spares for a new compressor were still in procurement at first gas. A minor seal failure forced a six-week shutdown that a readiness review would have flagged.
Links go to the publisher's official page (ISO, IEC, BSI, API, NFPA, HSE and others). Most standards must be bought from the publisher.
Take this briefing with you
A one-to-two page PDF summary: situation, diagram, key takeaways, consequences, examples and standards.