Project premise and basis of design: writing down what everyone is assuming

2026-11-15

Most scope disputes start with an unwritten assumption. A project premise and basis of design capture the key decisions early and make changes visible.

The situation

The project premise states the business objectives and constraints. The basis of design (BoD) sets the technical inputs: feed compositions, capacities, design life, codes, site data and philosophies. Both must be agreed and placed under change control early.

Why write it down

Different disciplines, contractors and stakeholders carry different assumptions. Writing them down early prevents rework and disputes later.

Diagram: Project premise and basis of design
Figure: Atticus Energy, generic illustration.

Project premise

Covers the business objective, scope boundaries, givens and constraints, key decisions taken, and open decisions with owners. It is the reference for whether a proposed change is in scope.

Basis of design

Covers feed and product data, design capacities and turndown, environmental and site data, design codes and standards, and philosophies for operation, maintenance, safety and control.

Keeping them current

Both documents should be under change control. When an assumption changes, assess the impact, approve the change and reissue.

Brownfield specifics

For brownfield projects, include the condition of existing systems, interfaces with operating plant, tie-in requirements and shutdown windows.

Who reads them

Every new team member and every contractor. If they cannot find an answer in these documents, the documents need updating.

Key Takeaways

  • Write assumptions down before design starts.
  • The premise defines scope; the basis defines design.
  • Place both under formal change control.
  • Include interfaces and shutdown windows for brownfield work.

How Atticus helps

We prepare project premises and basis-of-design documents and run the reviews that lock decisions in at each gate.

Real-world examples

Documented incident

Sleipner A gravity base structure (1991)

The Sleipner A structure failed in a controlled test after a design calculation error went unchecked. Clear design bases and independent verification of key assumptions are essential.

Read the investigation / source
Illustrative scenario

wrong feed basis

A processing plant was designed on a gas composition sample that turned out to be unrepresentative. Higher CO2 required an amine unit to be added after FID, with major cost and schedule impact.

If you get it wrong

  • Redesign and rework late in the project.
  • Facilities that cannot meet product or capacity targets.
  • Disputes with contractors over changed bases.
  • Operability issues for the life of the asset.

Relevant standards

Links go to the publisher's official page (ISO, IEC, BSI, API, NFPA, HSE and others). Most standards must be bought from the publisher.

Further reading

Take this briefing with you

A one-to-two page PDF summary: situation, diagram, key takeaways, consequences, examples and standards.