Lost production is rarely one big event. It is many small trips and slowdowns. Recording them consistently and analysing the repeat offenders is where the gains are.
The situation
Unscheduled deferment is production lost to unplanned events: trips, failures and process upsets. Systematic root cause analysis (RCA) of significant events, with data captured to ISO 14224 taxonomy, drives the reliability improvements that recover that production.
Deferment is production lost against the potential of the asset. Planned deferment comes from scheduled shutdowns and maintenance. Unscheduled deferment comes from trips, failures, process upsets and external causes.
Every loss needs a start and end time, volume, system, equipment and an agreed cause code. Without consistent coding, the biggest problems hide in "other".
Sort losses by total volume and by frequency. A few systems usually account for most of the loss. These are the candidates for root-cause analysis.
Use a structured method such as cause-and-effect trees or "five whys". Look beyond the failed part to why it failed: design, operating conditions, maintenance strategy or procedures.
Actions should remove the cause, not just restore the equipment. After the fix, track whether the loss category actually falls.
A short weekly review of deferment by operations and maintenance keeps attention on the top offenders and stops new problems becoming chronic.
We set up deferment accounting, run root-cause analyses on chronic losses, and support improvement programmes for producing assets.
At Husky Superior, the CSB investigation traced an explosion during FCC unit shutdown to an eroded slide valve that allowed air and hydrocarbons to mix. A good RCA goes past the immediate failure to the inspection and design factors behind it.
Read the investigation / sourceA compressor tripped on high vibration twelve times in a year. Each trip was reset without investigation. A single RCA found a misaligned coupling and a faulty probe, and fixing both recovered several days of production a year.
Links go to the publisher's official page (ISO, IEC, BSI, API, NFPA, HSE and others). Most standards must be bought from the publisher.